Ground-mount solar power plant

Ground mount solar plants offer the highest energy density and lowest levelised cost of electricity (LCOE) of any solar deployment model. With abundant land availability in the Antalya region and one of Turkey's highest solar irradiance levels (GHI ~1,850 kWh/m²/yr), ground mount projects deliver exceptional returns for landowners, investors, and industrial self-consumers alike.

Antalya Solar Energy Co. has delivered ground mount projects from 1 MWp on agricultural land to a 10 MWp utility-scale plant in Burdur. Our in-house engineering, procurement, construction, and commissioning capabilities mean complete project execution under a single EPC contract.

How Ground Mount Systems Work

Mono-crystalline panels are mounted on galvanised steel piling or ballasted foundations at an optimised tilt angle (typically 25–30° for Antalya latitude). Strings feed to central or string inverters located in weather-proof combiner/inverter stations. MV transformers step up voltage for grid injection, and a dedicated HV connection cable runs to the nearest TEİAŞ/TEDAŞ transformer substation.

For systems with a YEKDEM or YEK-G market licence, production is metered and sold to the grid at the applicable renewable energy support tariff or bilateral market price.

System Options & Technologies

  • Fixed-Tilt: Lowest CapEx, optimal for sites with minimal shading and flat terrain. Typical yield: 1,500–1,600 kWh/kWp/yr in Antalya.
  • Single-Axis Tracker (SAT): 15–25% higher yield vs. fixed tilt. East-west tracking of the sun. Higher CapEx but superior LCOE on large sites (>2 MWp).
  • Bifacial Modules: 5–12% additional yield from rear-side reflection (especially on light-coloured sandy/gravel ground). We model bifacial gain in PVsyst for every project.
  • Central vs. String Inverters: String inverters (Huawei SUN2000-100KTL) offer better MPPT granularity and easier maintenance. Central inverters (1.25 MVA) lower installation cost for very large plants.

Full EPC Process

1
Land Assessment: Topographic survey, soil bearing capacity, zoning classification (agricultural, forestry, treasury), and grid connection study (TEİAŞ/TEDAŞ proximity).
2
Feasibility & Licensing: EPDK pre-licence application (for systems >1 MW), environmental impact assessment (ÇED) if required, and TEDAŞ connection agreement.
3
IFC Engineering: PVsyst P50/P90 yield study, civil design (roads, drainage, fencing), single-line diagram, MV network design, and protection relays.
4
Procurement: Modules, string inverters, racking, DC/AC cables, MV transformer, SCADA system, perimeter fencing, CCTV.
5
Civil & Electrical Works: Pile driving/foundation, racking, module installation, DC stringing, inverter wiring, MV cable laying, substation erection.
6
Commissioning: PAC testing, SCADA integration, TEİAŞ/TEDAŞ commissioning inspection, meter certification.

Technical Specifications

ParameterValue
Plant Capacity Range1 MWp – 50 MWp (single EPC contract)
Module TechnologyBifacial Mono PERC / TOPCon, 580–700 Wp
Inverter Range100 kW string (Huawei) to 2.5 MW central (SMA)
Racking SystemsSchletter FS, Clenergy, Baja Solar Structures (hot-dip galvanised)
Tracker OptionNextracker NX Horizon, Array Technologies DuraTrack
Typical Specific Yield1,550–1,750 kWh/kWp/yr (SAT with bifacial)
Grid Voltage34.5 kV or 154 kV (project-dependent)
SCADAHuawei FusionSolar / custom Modbus/IEC 61850

Financial Returns — 5 MWp Example

  • CapEx: ~₺60M (₺12,000/kWp all-inclusive EPC)
  • Annual Generation: ~7,750 MWh (P50, fixed tilt)
  • Annual Revenue: ~₺27.1M at 3.5 ₺/kWh
  • Simple Payback: 2.2 years
  • 25-year cumulative revenue: ~₺677M (with tariff escalation)
  • Project IRR: 35–42% (depending on financing structure)

Why Antalya Solar Energy Co.

  • Completed 6 utility-scale ground mount projects (1–10 MWp) with zero grid-connection delays
  • In-house EPDK licensing team — we have handled 12 licence applications successfully
  • Bankable IFC-grade engineering for project finance
  • Long-term O&M with PR guarantees and drone inspection
  • Local construction teams — no mobilisation delays

Frequently Asked Questions

Solar farms can be built on marginal agricultural land (Class 6–8), pasture land with Ministry of Agriculture permission, and industrial/treasury land. Prime agricultural land (Class 1–4) requires special cabinet-level permission. We conduct land zoning analysis in the first phase of every project.

Systems up to 1 MW are exempt from EPDK generation licence (unlicensed, net-metering generation). Systems between 1–10 MW require a preliminary licence from EPDK followed by a generation licence. Systems above 10 MW follow a full EPDK licensing procedure with TEİAŞ connection study.

From contract signature: 3–4 months for licensing, 2 months for procurement, 3 months for civil and electrical construction. Total: 8–12 months. EPDK licensing (for systems over 1 MW) can add 6–18 months depending on the capacity queue.

Yes — agrivoltaic (dual-use) systems allow solar panels to share land with crops, livestock grazing, or beekeeping. We design agrivoltaic configurations with raised mounting structures (3m clearance) to maintain agricultural machinery access.

Ground-Mount Solar: Investing in a Utility-Scale Power Plant

A ground-mount solar power plant is an energy-generation facility — ranging in scale from kWp to MW — built on non-cultivated land suitable for energy investment. In line with Turkey's 2030 targets, ground-mount solar offers attractive opportunities to both private and institutional investors. For those holding idle land in inland provinces such as Antalya, Isparta, and Burdur, a ground-mount plant can become a powerful source of passive income.

Ground-Mount Project Sizes & Cost Table

Project Scale Land (Dönüm) Investment Annual Generation Annual Revenue
500 kWp (Small Site)4–5 dönüm₺5M775,000 kWh₺2.7M
1 MWp8–10 dönüm₺9.5M1,550,000 kWh₺5.4M
5 MWp40–50 dönüm₺42M7,750,000 kWh₺27M
10 MWp80–100 dönüm₺80M15,500,000 kWh₺54M

* Based on a ₺3.50/kWh grid sale tariff, a 15% loss factor, and an Antalya yield of 1,550 kWh/kWp.

Ground-Mount Licensing & Permitting Process

There are two principal regulatory routes for ground-mount solar projects in Turkey:

Site Suitability Criteria for Ground-Mount Solar

The technical and legal criteria that determine whether a land parcel is suitable for a solar plant include:

Ground-Mount Operations & Maintenance (O&M)

We provide operations and maintenance (O&M) services for commissioned ground-mount plants:

Explore Your Ground Mount Solar Opportunity

Share your land location and power goals — we'll prepare a full feasibility study including irradiance analysis, grid connection assessment, and financial model.

+90 534 504 01 06
WhatsApp