
Ground mount solar plants offer the highest energy density and lowest levelised cost of electricity (LCOE) of any solar deployment model. With abundant land availability in the Antalya region and one of Turkey's highest solar irradiance levels (GHI ~1,850 kWh/m²/yr), ground mount projects deliver exceptional returns for landowners, investors, and industrial self-consumers alike.
Antalya Solar Energy Co. has delivered ground mount projects from 1 MWp on agricultural land to a 10 MWp utility-scale plant in Burdur. Our in-house engineering, procurement, construction, and commissioning capabilities mean complete project execution under a single EPC contract.
Mono-crystalline panels are mounted on galvanised steel piling or ballasted foundations at an optimised tilt angle (typically 25–30° for Antalya latitude). Strings feed to central or string inverters located in weather-proof combiner/inverter stations. MV transformers step up voltage for grid injection, and a dedicated HV connection cable runs to the nearest TEİAŞ/TEDAŞ transformer substation.
For systems with a YEKDEM or YEK-G market licence, production is metered and sold to the grid at the applicable renewable energy support tariff or bilateral market price.
| Parameter | Value |
|---|---|
| Plant Capacity Range | 1 MWp – 50 MWp (single EPC contract) |
| Module Technology | Bifacial Mono PERC / TOPCon, 580–700 Wp |
| Inverter Range | 100 kW string (Huawei) to 2.5 MW central (SMA) |
| Racking Systems | Schletter FS, Clenergy, Baja Solar Structures (hot-dip galvanised) |
| Tracker Option | Nextracker NX Horizon, Array Technologies DuraTrack |
| Typical Specific Yield | 1,550–1,750 kWh/kWp/yr (SAT with bifacial) |
| Grid Voltage | 34.5 kV or 154 kV (project-dependent) |
| SCADA | Huawei FusionSolar / custom Modbus/IEC 61850 |
Solar farms can be built on marginal agricultural land (Class 6–8), pasture land with Ministry of Agriculture permission, and industrial/treasury land. Prime agricultural land (Class 1–4) requires special cabinet-level permission. We conduct land zoning analysis in the first phase of every project.
Systems up to 1 MW are exempt from EPDK generation licence (lisanssız üretim). Systems between 1–10 MW require a preliminary licence from EPDK followed by a generation licence. Systems above 10 MW follow a full EPDK licensing procedure with TEİAŞ connection study.
From contract signature: 3–4 months for licensing, 2 months for procurement, 3 months for civil and electrical construction. Total: 8–12 months. EPDK licensing (for systems over 1 MW) can add 6–18 months depending on the capacity queue.
Yes — agrivoltaic (dual-use) systems allow solar panels to share land with crops, livestock grazing, or beekeeping. We design agrivoltaic configurations with raised mounting structures (3m clearance) to maintain agricultural machinery access.
Arazi güneş enerji santrali (arazi GES), tarım yapılmayan, enerji yatırımına uygun arazilerde kurulan, kWp ile MW arası ölçeklerde enerji üretim tesislerini ifade eder. Türkiye'nin 2030 hedefleri doğrultusunda arazi GES yatırımları hem bireysel hem kurumsal yatırımcılar için cazip fırsatlar sunmaktadır. Antalya, Isparta ve Burdur gibi iç bölgelerde boş arazisi bulunan yatırımcılar için arazi GES güçlü bir pasif gelir kaynağına dönüşebilir.
* ₺3,50/kWh şebeke satış tarifesi, %15 kayıp katsayısı, 1.550 kWh/kWp Antalya verimi baz alınmıştır.
Türkiye'de arazi GES projelerinde iki temel yasal yol mevcuttur:
Bir arazi parselinin GES yatırımına uygunluğu belirleyen teknik ve hukuki kriterler:
Devreye alınan arazi GES tesisi için operasyon ve bakım (O&M) hizmetleri sunuyoruz:
Real completed installations by Solar Nexo team in Antalya & Alanya region
Watch Solar Nexo team completing real installations across Antalya & Alanya
Share your land location and power goals — we'll prepare a full feasibility study including irradiance analysis, grid connection assessment, and financial model.