The Antalya Solar Energy EPC Process: From Site Survey to Commissioning

What actually happens between the first site visit and the day your plant is energised? A transparent, phase-by-phase walkthrough of a commercial solar EPC project in Antalya.

For a first-time buyer, commissioning commercial solar energy in Antalya can look like a black box: a contract is signed, a few months pass, and a plant appears on the roof. In reality, an EPC project is a carefully sequenced chain of engineering, regulatory and construction steps. Understanding that chain helps you plan internal resources, set realistic expectations with management and recognise a well-run project when you see one.

EPC stands for Engineering, Procurement and Construction. Under an EPC contract, one company takes responsibility for delivering a working plant. Below we walk through the seven phases we follow on every commercial project for solar energy in Antalya, from a 450 kW factory roof to our 4.5 MW industrial rooftop and 2.4 MW ground-mount plant.

Phase 1: Initial consultation and site survey

The process starts with your data: twelve months of electricity invoices, the site address and, if available, roof drawings or building plans. After a preliminary review, our engineer visits the site to:

  • Measure usable roof or land area and record obstructions such as skylights, vents and parapets
  • Inspect the roof covering, purlins and main structure for load-bearing capacity
  • Assess shading from neighbouring buildings, trees and terrain
  • Inspect the main distribution board, transformer and metering arrangement
  • Identify cable routes, inverter locations and crane access

The survey is free and non-binding. Its quality determines the reliability of everything that follows.

Phase 2: Feasibility study and proposal

Back in the office, we simulate the plant's yield for the specific site, match it hourly against your consumption profile and build a financial model. The feasibility report typically contains a preliminary layout, P50 and P90 yield estimates with a loss breakdown, the expected self-consumption ratio, an equipment specification, a payback range and a list of scope inclusions and exclusions. We present the report in a meeting with your technical and financial decision-makers, answer questions and adjust the design if priorities change.

Phase 3: Contract and grid application

Once the contract is signed, the regulatory track begins. We prepare the connection application to the regional distribution company (EDAŞ) under the unlicensed generation framework. The distribution company evaluates network capacity and issues a connection opinion; once its conditions are met, the connection agreement is signed and the electrical project is submitted for approval. The duration of this phase varies by region, plant size and network capacity, and it often determines the overall timeline more than construction does. Because rules change periodically, we confirm the current EPDK requirements at this stage.

Phase 4: Detailed engineering and procurement

In parallel with the regulatory process, the design is finalised: string configuration, cable sizing, protection coordination, mounting system details, structural verification and single-line diagrams. Equipment is then ordered according to the approved specification. For larger plants, deliveries are scheduled in stages so that modules and structures arrive when the crews need them, reducing storage requirements and damage risk on site.

Phase 5: Construction

Construction follows a written method statement agreed with your facility team. A typical rooftop sequence is:

  1. Site setup, safety barriers, roof access and fall-protection systems
  2. Installation of the mounting system on the roof profile or ballast
  3. Module installation and DC string cabling
  4. Inverter installation, earthing and surge protection
  5. AC cabling and connection preparation at the main distribution board
  6. Monitoring hardware and communication cabling
  7. Final tidy-up and photo documentation of all concealed works

Production usually continues normally during construction. The final connection to the main board is scheduled at an agreed time, often outside shifts or at the weekend, to minimise disruption.

Phase 6: Testing, commissioning and acceptance

Before energisation, every string is tested for open-circuit voltage, current and insulation resistance, and earthing continuity is verified. Inverters are configured with the protection settings required by the distribution company. We then coordinate the acceptance inspection with TEDAŞ or the authorised body. Once acceptance is complete and the bidirectional metering is in place, the plant is energised and starts turning Antalya solar energy into savings.

Phase 7: Handover and O&M

At handover you receive as-built drawings, test and commissioning records, equipment warranty documents, an operation manual and access to the monitoring platform. We train your team on the essentials. If you sign an O&M contract, our engineers take over remote monitoring, schedule preventive inspections and cleaning, and report performance ratio against the design model.

What a well-run Antalya solar energy project looks like for the client

From your perspective, a well-managed EPC project is predictable. You receive a milestone plan at contract stage and short written updates whenever an approval arrives or a schedule changes. Site work starts only after a joint kick-off meeting covering access, safety rules, crane slots and contact persons. Any deviation from the approved design is discussed before it is built, not explained afterwards. And at handover, the documentation is complete enough that another engineer could maintain the plant without calling us. If a contractor cannot describe how they will deliver these basics, treat that as a warning sign.

Indicative timeline

PhaseWhat drives the durationYour contribution
Survey and feasibilityData availability, site complexityInvoices, drawings, site access
Grid application and approvalsDistribution region, plant size, network capacitySubscriber documents, signatures
Engineering and procurementEquipment lead times, structural checksApproval of final design
ConstructionPlant size, roof access, weatherSite coordination, staff briefing
Commissioning and acceptanceInspection schedulingPresence at inspection

For a mid-sized industrial roof, the overall process typically takes a few months, with the regulatory phase as the main variable. We issue a project-specific milestone plan at contract stage.

Tips for a smooth EPC project

  • Collect twelve months of invoices before the first meeting; they are the foundation of the whole design.
  • Check your building's zoning and permit status early, especially for older or extended buildings.
  • Confirm that your main distribution board has space for the solar connection, or budget for an upgrade.
  • Nominate one internal contact who can make decisions and coordinate access.
  • Plan construction around critical production periods or peak hotel season.

All articles

Blog

Latest from the blog

Start with a free feasibility review

Share twelve months of electricity bills and your site location. Our engineers will assess roof or land suitability, outline a plant size and arrange a free on-site survey.